Pipeline replacement to begin in Hogan Park

Centurion Pipeline is scheduled to begin their pipeline replacement project in Hogan Park in December.

This will affect the use of several baseball fields in the southwest corner of the park. There will be times during the project where Redfern Parkway will be closed to thru traffic. Parking to the east of the baseball fields will be accessed from North Lamesa Road.

Sibley Circle Parkway, which runs in front of the Sibley Nature Center and the Hispanic Cultural Center, leading to the dog parks and playground, will remain open as they will bore in this area.

Removal of the lines will start in the beginning of December; installation of the polylines will begin mid-January to early February; crude lines will be installed in late April. The estimated completion date is the first week of June.