Re-tooled FutureGen

Comments 0 | Recommend 0

Energy Department unveils smaller-scale plans for clean coal plants

ST. LOUIS The Department of Energy unveiled its blueprint Wednesday for spending up to $1.3 billion on multiple clean-coal power plants that would capture carbon emissions and permanently store them underground.

The announcement, launching two weeks of public comment over the revised plan for the project known as FutureGen, came despite pledges by U.S. Sen. Dick Durbin to scuttle the effort. The Democrat stands convinced a town in his home state of Illinois deserved the project - all of it.

FutureGen's developers - an alliance of a dozen big power and coal companies - tapped Mattoon, Ill., as the site in December. But the Energy Department quickly pulled the plug, citing costs that had ballooned to $1.8 billion, nearly double the original price tag.

The department considers it smarter to spread the taxpayer money around to several smaller projects throughout the United States.

On Wednesday, Bud Albright, an undersecretary for the department, said Mattoon is out of the picture unless a developer wants to build a power plant there, then apply to partner with the Department of Energy.

"The direction we're going - let me make absolutely clear if there's any question - we're fully committed to. We think it's a better direction," he said.

"It's a faster way to go" because it instantly commercializes the technology instead of merely experimenting with it at a research site in Mattoon, Albright said.

Lawrence Pacheco, a spokesman for the FutureGen Alliance that picked Mattoon over three other finalists - Odessa and Jewett in Texas and Tuscola in Illinois - countered that the fight for Mattoon was anything but over.

Durbin, the Senate's second-ranking Democrat, has threatened to block White House appointments to the Energy Department while looking for a way to pass legislation to keep the project afloat until the next president takes office in January.

Durbin said Wednesday evening that the new plan was unworkable and cannot be taken seriously.

"They wouldn't even receive applications from the new sites until four weeks before the current administration ends," he said in a telephone interview. "It isn't a serious plan - it's merely a mask for their embarrassment."

"Our goal is to keep the location in Mattoon until this administration packs and leaves town," said Durbin, noting that authorities have invested five years of study, as well as federal and state funds, in the Mattoon site.

FutureGen will be debated Thursday, when Durbin is expected to take part in a discussion of the project with the Senate's subcommittee on energy and water development appropriations.

Durbin and the rest of the Illinois delegation must try to keep the project alive until June, when the DOE can legally cancel its contract with the companies making up the FutureGen Alliance.

Wednesday's announcement "is simply another step in the department's ill-advised attempt to move the ball downfield before time expires," U.S. Rep. Tim Johnson, an Illinois Republican, said in a statement. "A real commitment to cutting-edge carbon capture demands" a legislative fight on Mattoon's behalf.

Pacheco said the political pressure on the Department of Energy - and the fact Congress has to sign off on the department's retooled plan - leaves the alliance "cautiously optimistic" Mattoon will win.

"We've gotten a lot of good feedback from members on the Hill," Pacheco said. "And there have been a number of hearings over the last month in which members of Congress have expressed pretty deep skepticism about DOE's plans to restructure FutureGen."

Durbin and others have long suspected politics and President Bush's Texas roots were behind the decision to restructure FutureGen.

Under the new plan, developers of power plants would have to apply to the Department of Energy for a slice of the $1.3 billion.

Albright said it wasn't clear how many projects the money would help fund.

He said each plant will permanently store underground at least a million metric tons of carbon dioxide a year. The sites also must capture at least 81 percent of the carbon dioxide, with a goal of reaching 90 percent, Albright said.

The plant also must generate at least 300 megawatts of electricity, just 25 megawatts more than the original plan.

Anyone wanting to weigh in the Energy Department's blueprint may do so until May 21.

The department expects to formally begin soliciting applications from developers this summer, with the projects to be decided by the end of the year.

"I want it to be good, hard competition, and we want pencils to be as sharp as possible as they put their bids in," Albright said. "We're trying to get a good deal for taxpayers and wanting to do the right thing for the environment."


See archived 'Local News' stories »
 


Reader Comments
Many of you have expressed concerns about some of the harsh anonymous comments from readers. To remedy that, we are introducing new features. You can create your own blog, publish your news and share your photos with the community. Once you fill out a simple form and leave a verifiable e-mail address, you can set up your profile page. It will display all of your contributions and allow you to track issues and easily connect with others.

We want our site to be a place where people discuss and debate ideas that foster stronger communities. We built this for you. Please take care of it. Tolerate broad thinking, but take action against obscene or hateful material. Make it a credible and safe place worth preserving and sharing.


ADVERTISEMENT 
Featured Events

 
  • Find an Event
Publish Your Stuff
ADVERTISEMENT 
ADVERTISEMENT 
Poll
Stocks
Games
Good times ahead?
Are you hopeful for a long playoff run by both the Odessa High and Permian football teams? Vote and tell us why or why not in an email to oaletters@oaoa.com.
Yes
No
Enter The Code To Vote
 
Read Related Article
ADVERTISEMENT 
powered by
google
Search
        Search: Web    Site